Rural Electrification Project (USAID financed), Renamed the Power Distribution Program

 

Year of Engagement: 1984-93
Name of Project: Rural Electrification Project (USAID financed), Renamed the Power Distribution Program
Any Other Pertinent information:

EMMAY is worked as a sub contractor and consultant on an $30 Million consulting assignment . EMMAY put in about 25% of  the Pakistan effort which is 50-70% of the total and was responsible for institution Building training and Financial/Commercial Aspects and the logistic trail, including Procurement and inventory control and computerization

  • Prepared the HQs institutional reorganization plan for power Distribution wing and laid down requirements for ensuring implementations of accepted recommendations.
  • Management analysis and planning was done a part of writing reports on the power distribution organization of wapda
  • Involve in the initial planning of MIS as part of the management service staff function.
  • Financial analysis carried out determined the financial position of power wing.
  • Financial audit conducted  to highlight deficiencies in accounting & financial functions.
  • Re-modeled the financials statements to bring them in line with those of American Electric Power Corpn.
  • Computed the tariff cost of service chargeable to different categories of customers.
  • Although not involved in the initial project design, but as work processed, provided inputs to modify the same considerably.
  • Fully involved in the administrative & institutions analysis as well as reports resulting from the analysis.
  • Questioners were prepared to formulate Model Divisions Reorganizations.
  • Produced the model division Reorganization plan for Muridke and sheikhupura  Divisions.
  • Prepared institutional and financial reports.
  • Project management & monitoring – Prepared all the initial functions Gantt Charts interrelationships.
  • Level of effort problems, time Horizon problems , coordinative  problems with WAPDA at highest level were also taken care of.
  • In the  course of the assignment had several dialogues with member (Power) of WAPDA with the federal Ministry. 